City Dam Maintenance Pushed To Spring 2027; Winter Called 'Inadvisable'
Public Works delayed the $127,000 repair job on the Fox River dam, citing cold weather and an eight-week timeline.
WAUKESHA — The city's Public Works Department announced Tuesday that routine maintenance on the municipal dam along the Fox River, originally scheduled for this fall, will instead take place in spring 2027, citing cold-weather conditions that officials say make the repairs "inadvisable" before April.
City Engineer Frank Novotny said the delay was driven primarily by concrete curing requirements, which slow significantly once temperatures drop below 40 degrees. He declined to specify which stretch of the five-month gap between the original schedule and the new one accounted for the difference.
'Seasonal Weather Making Repairs Inadvisable'
"The work requires the spillway gates to stay open for extended periods. Doing that in January isn't something we'd recommend attempting twice."
— Frank Novotny, Waukesha City Engineer
The project, budgeted at $127,000, covers resurfacing of the dam's downstream face and replacement of two gate actuators that have been in service since 1994. Novotny said the work is expected to take approximately eight weeks once it begins, weather permitting, which he described as "a planning assumption, not a promise."
Residents Surprised City Has A Dam
News of the postponement prompted a round of confusion among residents reached for comment, several of whom said they had not previously known the city operated a dam at all.
"Where exactly is this dam? I've lived off Sunset Drive for nineteen years and I feel like that's something I'd have noticed."
— Carol Niemitz, 58, Sunset Drive homeowner
Novotny said the structure, which regulates water levels upstream of downtown, is inspected twice a year and has not required emergency repairs since a 2019 valve replacement. He added that the department fields "maybe four or five" calls a year from residents asking whether the dam is the same thing as the rapids near Frame Park. It is not.
Eight-Week Window, $127,000 Price Tag
The $127,000 cost will be drawn from the department's existing infrastructure maintenance budget, and no additional borrowing or special assessment is required, according to a one-page summary distributed to the Common Council ahead of Tuesday's meeting. Novotny said the figure includes a 12 percent contingency for "anything we find once the gates are actually open," which he noted has happened on three of the last four maintenance cycles.
Council members present raised no objections to the postponement. Councilman Gary Puchalski asked whether the eight-week estimate accounted for the possibility of a second delay, a question Novotny answered by saying the department "builds in realistic expectations" without further elaborating.
Next Steps
Public Works said it will issue a formal notice to residents along the affected stretch of riverbank roughly 30 days before work begins in March, and that normal water flow and recreational access will not be affected until the project starts. Novotny said his office would provide an update "closer to spring," which he confirmed does have a more specific date attached to it internally, though he declined to share it Tuesday.
The maintenance had previously been penciled in for October before being pushed first to November, then, as of this week, to next year entirely. Novotny said the department does not consider that a pattern.